CompTIA PK0-005 (CompTIA Project+) Practice Test 94

Question 930

With historical mean velocity 22 points per sprint, a service quality and software-release reporting team has 180 points remaining before two comparable sprints. What backlog is forecast after two sprints, assuming no additional stories?

  1. 44 points
  2. 180 points
  3. 136 points
  4. 158 points

Explanation

Correct Answer

C:

Forecast completed=2×22=44; remaining=180−44=136. These stated figures yield 136 points for the requested remaining forecast backlog in the service quality and software-release reporting case.

Incorrect Answers

A:

This is amount completed, not remaining. The resulting 44 points does not match the requested remaining forecast backlog for the service quality and software-release reporting: the governing arithmetic is Forecast completed=2×22=44; remaining=180−44=136, yielding 136 points.

B:

This ignores forecast completion. The resulting 180 points does not match the requested remaining forecast backlog for the service quality and software-release reporting: the governing arithmetic is Forecast completed=2×22=44; remaining=180−44=136, yielding 136 points.

D:

This assumes only one sprint is available. The resulting 158 points does not match the requested remaining forecast backlog for the service quality and software-release reporting: the governing arithmetic is Forecast completed=2×22=44; remaining=180−44=136, yielding 136 points.

Question 931

The asset-tracking solution team has a specific outstanding requirement: perform a quick post-deployment check that core functions are operational. At the planning review, which action or practice is the most appropriate response?

  1. Smoke testing
  2. Stress testing
  3. Regression testing
  4. User acceptance testing

Explanation

Correct Answer

A:

Smoke testing fits the asset-tracking solution requirement to perform a quick post-deployment check that core functions are operational; operational mechanism: Smoke tests detect obvious failures before time-consuming deeper testing proceeds; specific limitation: Passing them does not demonstrate every regression case or peak-load requirement.

Incorrect Answers

B:

Stress testing is intended to observe system behavior beyond normal expected load and identify failure points, not to meet the asset-tracking solution requirement to perform a quick post-deployment check that core functions are operational; the practical reason is: Stress testing pushes conditions to extremes to explore resilience and recovery; important boundary: It is more aggressive than measuring normal workload performance.

C:

Regression testing is intended to detect whether a code update broke functionality that previously worked, not to meet the asset-tracking solution requirement to perform a quick post-deployment check that core functions are operational; operational mechanism: Regression testing repeats relevant existing checks after a change; specific limitation: It is different from proving only that the new feature works.

D:

User acceptance testing is intended to obtain business-user evidence that the delivered workflow meets agreed needs, not to meet the asset-tracking solution requirement to perform a quick post-deployment check that core functions are operational; the practical reason is: UAT validates a solution against the users' operational acceptance criteria; important boundary: Passing technical unit tests alone cannot demonstrate business fitness.

Question 932

Before using Personally identifiable information (PII) handling on the university learning portal, the steering group asks about its limitations. Which qualification specifically prevents an overbroad interpretation of this practice for the goal to protect customer records that can identify a particular person?

  1. A vendor's headquarters alone may not determine every applicable law.
  2. Contract language must be supported by practical access controls.
  3. Not all operational metrics are individually identifiable.
  4. Indefinite retention can conflict with privacy and storage duties.

Explanation

Correct Answer

C:

This is the actual limitation of Personally identifiable information (PII) handling when the university learning portal uses it to protect customer records that can identify a particular person; operational mechanism: PII controls govern collection, access, transfer, and retention of identifying data; specific limitation: Not all operational metrics are individually identifiable.

Incorrect Answers

A:

This warning concerns Regional privacy-law review used to check which jurisdiction's privacy rules apply to cross-border customer processing, not the specified Personally identifiable information (PII) handling used to protect customer records that can identify a particular person in the university learning portal; functional evidence: Jurisdictional review connects processing location and affected people to legal requirements; qualification to consider: A vendor's headquarters alone may not determine every applicable law.

B:

This warning concerns Confidentiality agreement used to bind participants to protect sensitive commercial information they receive, not the specified Personally identifiable information (PII) handling used to protect customer records that can identify a particular person in the university learning portal; operational mechanism: Confidentiality clauses establish enforceable duties to restrict disclosure; specific limitation: Contract language must be supported by practical access controls.

D:

This warning concerns Retention and secure disposal schedule used to specify how long sensitive project data is kept and how it is safely removed, not the specified Personally identifiable information (PII) handling used to protect customer records that can identify a particular person in the university learning portal; functional evidence: Retention controls tie storage duration and disposal to policy and law; qualification to consider: Indefinite retention can conflict with privacy and storage duties.

Question 933

A delivery resource plan tester has 15 planned productive workdays before go-live but has 3 leave days during that period. How many available workdays should the resource calendar show?

  1. 3 days
  2. 18 days
  3. 15 days
  4. 12 days

Explanation

Correct Answer

D:

Available days=15−3=12. These stated figures yield 12 days for the requested net available days in the delivery resource plan case.

Incorrect Answers

A:

This is leave time, not available time. The resulting 3 days does not match the requested net available days for the delivery resource plan: the governing arithmetic is Available days=15−3=12, yielding 12 days.

B:

Leave must not be added to available days. The resulting 18 days does not match the requested net available days for the delivery resource plan: the governing arithmetic is Available days=15−3=12, yielding 12 days.

C:

This overlooks leave. The resulting 15 days does not match the requested net available days for the delivery resource plan: the governing arithmetic is Available days=15−3=12, yielding 12 days.

Question 934

For the regional call-center cutover, a draft plan relies only on Confirm high-level solution design because the team wants to select a feasible architecture direction that meets the charter's major constraints. A reviewer identifies a separate unmet obligation: align the team on objectives, roles, constraints, and initial ways of working. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Conduct the kickoff meeting
  2. Project charter
  3. Review inherited project artifacts
  4. Confirm high-level solution design

Explanation

Correct Answer

A:

The regional call-center cutover plan must add Conduct the kickoff meeting to align the team on objectives, roles, constraints, and initial ways of working; its current Confirm high-level solution design is already intended to select a feasible architecture direction that meets the charter's major constraints; the practical reason is: A kickoff introduces shared project direction and working expectations; important boundary: It is not the contract-closeout event at the end of delivery.

Incorrect Answers

B:

Project charter is intended to formally authorize a project with objectives, high-level scope, and a named leader; that is different from the overlooked regional call-center cutover obligation to align the team on objectives, roles, constraints, and initial ways of working; operational mechanism: The charter establishes project legitimacy and overarching direction; specific limitation: Detailed work packages and full schedules are developed subsequently.

C:

Review inherited project artifacts is intended to identify existing contracts, requirements, and constraints before re-planning a handed-over project; that is different from the overlooked regional call-center cutover obligation to align the team on objectives, roles, constraints, and initial ways of working; the practical reason is: Reviewing inherited artifacts prevents accidental conflict with previous commitments; important boundary: A new team should not treat prior approvals as nonexistent.

D:

Confirm high-level solution design is already serving select a feasible architecture direction that meets the charter's major constraints in the regional call-center cutover; the corrected plan must also address the unmet obligation to align the team on objectives, roles, constraints, and initial ways of working; the practical reason is: Early solution design resolves critical technical assumptions for planning; important boundary: Detailed build specifications may still be refined later.

Question 935

The identity governance implementation team already uses PRINCE2 to govern an initiative through defined management stages and business-case justification. A new workstream must also embed security controls and scanning throughout an automated delivery pipeline. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. PRINCE2
  2. Waterfall
  3. DevSecOps
  4. Extreme programming (XP)

Explanation

Correct Answer

C:

Adding DevSecOps addresses the new identity governance implementation need to embed security controls and scanning throughout an automated delivery pipeline; PRINCE2 already serves the separate need to govern an initiative through defined management stages and business-case justification; the practical reason is: DevSecOps integrates security practices into development and operations workflows; important boundary: It shifts security checks earlier instead of postponing them until after release.

Incorrect Answers

A:

PRINCE2 is already present in the identity governance implementation to govern an initiative through defined management stages and business-case justification; repeating it does not fulfill the distinct requirement to embed security controls and scanning throughout an automated delivery pipeline; functional evidence: PRINCE2 emphasizes continued business justification, roles, stage controls, and exceptions; qualification to consider: It is a governance-oriented project method rather than a source-code branching practice.

B:

Waterfall would instead address deliver a tightly specified integration using planned sequential phase approvals; the identity governance implementation still needs to embed security controls and scanning throughout an automated delivery pipeline, in addition to its existing PRINCE2; the practical reason is: Waterfall commonly completes planned stages in sequence with formal stage outputs; important boundary: It is less accommodating of major late requirement changes than iterative approaches.

D:

Extreme programming (XP) would instead address improve code quality with pair programming, continuous integration, and test-first engineering; the identity governance implementation still needs to embed security controls and scanning throughout an automated delivery pipeline, in addition to its existing PRINCE2; functional evidence: Extreme programming applies disciplined engineering practices and rapid developer feedback; qualification to consider: It is a software development practice set, not an enterprise portfolio framework.

Question 936

For the multisite wireless upgrade, a draft plan relies only on Change log because the team wants to trace proposed changes, approvals, status, and implementation references. A reviewer identifies a separate unmet obligation: explain progress, variance, major risks, decisions needed, and next actions to stakeholders. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Project dashboard
  2. Project status report
  3. Issue log
  4. Change log

Explanation

Correct Answer

B:

The multisite wireless upgrade plan must add Project status report to explain progress, variance, major risks, decisions needed, and next actions to stakeholders; its current Change log is already intended to trace proposed changes, approvals, status, and implementation references; operational mechanism: A status report provides narrative context around delivery conditions; specific limitation: It is not normally a live system of record for individual code revisions.

Incorrect Answers

A:

Project dashboard is intended to present a compact set of current indicators and exceptions across project workstreams; that is different from the overlooked multisite wireless upgrade obligation to explain progress, variance, major risks, decisions needed, and next actions to stakeholders; the practical reason is: A dashboard consolidates metrics for quick monitoring; important boundary: A narrative status report can supply more context behind the numbers.

C:

Issue log is intended to record active blockers with assignment, severity, progress, and resolution; that is different from the overlooked multisite wireless upgrade obligation to explain progress, variance, major risks, decisions needed, and next actions to stakeholders; operational mechanism: An issue log tracks realized delivery problems through closure; specific limitation: Forecast concerns alone belong in a risk register.

D:

Change log is already serving trace proposed changes, approvals, status, and implementation references in the multisite wireless upgrade; the corrected plan must also address the unmet obligation to explain progress, variance, major risks, decisions needed, and next actions to stakeholders; the practical reason is: A change log preserves the history of controlled alterations; important boundary: It cannot substitute for a risk response register.

Question 937

For the warehouse scanning upgrade, a draft plan relies only on Publish updated knowledge articles because the team wants to provide operational users with instructions matching the new application workflow. A reviewer identifies a separate unmet obligation: answer a newly raised executive question about a specific delivery issue. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Provide a targeted ad hoc report
  2. Report a risk trigger
  3. Conduct a phase-gate review
  4. Publish updated knowledge articles

Explanation

Correct Answer

A:

The warehouse scanning upgrade plan must add Provide a targeted ad hoc report to answer a newly raised executive question about a specific delivery issue; its current Publish updated knowledge articles is already intended to provide operational users with instructions matching the new application workflow; the practical reason is: Ad hoc reporting responds to an exceptional information need outside routine cadence; important boundary: It need not replace the normal reporting process.

Incorrect Answers

B:

Report a risk trigger is intended to tell decision makers that a named uncertainty's likelihood or impact has changed; that is different from the overlooked warehouse scanning upgrade obligation to answer a newly raised executive question about a specific delivery issue; the practical reason is: Risk reporting highlights evolving exposure and response triggers; important boundary: It is forward-looking unless the event already became an active issue.

C:

Conduct a phase-gate review is intended to check defined exit criteria before funding or starting the next controlled phase; that is different from the overlooked warehouse scanning upgrade obligation to answer a newly raised executive question about a specific delivery issue; operational mechanism: A phase gate provides a formal continue, redirect, or stop decision; specific limitation: Simply reaching a calendar milestone does not prove readiness.

D:

Publish updated knowledge articles is already serving provide operational users with instructions matching the new application workflow in the warehouse scanning upgrade; the corrected plan must also address the unmet obligation to answer a newly raised executive question about a specific delivery issue; operational mechanism: Knowledge bases turn rollout learning into repeatable accessible procedures; specific limitation: Old instructions can misdirect staff after process changes.

Question 938

For the supplier onboarding portal, a draft plan relies only on Mission-and-values alignment because the team wants to test whether a proposed initiative supports the organization's declared purpose. A reviewer identifies a separate unmet obligation: identify applicable sustainability or sector regulations before committing to a design. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Controlled facility access
  2. Mission-and-values alignment
  3. Regulatory standards check
  4. Community impact consultation

Explanation

Correct Answer

C:

The supplier onboarding portal plan must add Regulatory standards check to identify applicable sustainability or sector regulations before committing to a design; its current Mission-and-values alignment is already intended to test whether a proposed initiative supports the organization's declared purpose; operational mechanism: Regulatory review incorporates external compliance obligations into project planning; specific limitation: Company preferences cannot override mandatory legal requirements.

Incorrect Answers

A:

Controlled facility access is intended to restrict entry to server rooms to permitted personnel using badges and access logs; that is different from the overlooked supplier onboarding portal obligation to identify applicable sustainability or sector regulations before committing to a design; functional evidence: Facility controls protect physical infrastructure against unauthorized presence; qualification to consider: Digital login restrictions alone cannot stop someone entering a secure room.

B:

Mission-and-values alignment is already serving test whether a proposed initiative supports the organization's declared purpose in the supplier onboarding portal; the corrected plan must also address the unmet obligation to identify applicable sustainability or sector regulations before committing to a design; operational mechanism: Mission alignment compares project outcomes with the organization's stated direction; specific limitation: An attractive technology can still be strategically inappropriate.

D:

Community impact consultation is intended to gather feedback from residents affected by data-center building or installation work; that is different from the overlooked supplier onboarding portal obligation to identify applicable sustainability or sector regulations before committing to a design; functional evidence: Community consultation reveals local social effects before irrevocable choices; qualification to consider: A narrow engineering assessment may miss community concerns.

Question 939

The partner API integration team already uses Printed meeting packet to provide approved reference materials to participants in a network-restricted location. A new workstream must also publish living troubleshooting instructions that many support staff can maintain. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Wiki knowledge base
  2. Printed meeting packet
  3. Spreadsheet
  4. Shared file repository

Explanation

Correct Answer

A:

Adding Wiki knowledge base addresses the new partner API integration need to publish living troubleshooting instructions that many support staff can maintain; Printed meeting packet already serves the separate need to provide approved reference materials to participants in a network-restricted location; the practical reason is: Wikis organize linked operational knowledge with accessible revision history; important boundary: Their access and editorial rules should protect sensitive information.

Incorrect Answers

B:

Printed meeting packet is already present in the partner API integration to provide approved reference materials to participants in a network-restricted location; repeating it does not fulfill the distinct requirement to publish living troubleshooting instructions that many support staff can maintain; functional evidence: Print media allows offline distribution of fixed information; qualification to consider: Revision and secure disposal become important once printed.

C:

Spreadsheet would instead address perform tabular cost calculations and resource forecasts with transparent formulas; the partner API integration still needs to publish living troubleshooting instructions that many support staff can maintain, in addition to its existing Printed meeting packet; functional evidence: Spreadsheets support numeric modeling, filtering, and comparisons; qualification to consider: They can introduce formula and version risks if poorly controlled.

D:

Shared file repository would instead address give authorized collaborators a central location for working documents; the partner API integration still needs to publish living troubleshooting instructions that many support staff can maintain, in addition to its existing Printed meeting packet; the practical reason is: File sharing centralizes content access and permissions across a team; important boundary: It should be governed by classification and retention rules.

Question 940

For the customer-support application release, a draft plan relies only on Work breakdown structure (WBS) because the team wants to decompose a fixed delivery scope into manageable work packages for estimating. A reviewer identifies a separate unmet obligation: maintain an ordered inventory of agile product features awaiting implementation. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Detailed scope statement
  2. Transition and release plan
  3. Prioritized product backlog
  4. Work breakdown structure (WBS)

Explanation

Correct Answer

C:

The customer-support application release plan must add Prioritized product backlog to maintain an ordered inventory of agile product features awaiting implementation; its current Work breakdown structure (WBS) is already intended to decompose a fixed delivery scope into manageable work packages for estimating; functional evidence: The backlog captures work candidates and their relative product priority; qualification to consider: Not every item is a committed sprint deliverable.

Incorrect Answers

A:

Detailed scope statement is intended to specify boundaries, major deliverables, assumptions, and exclusions for project execution; that is different from the overlooked customer-support application release obligation to maintain an ordered inventory of agile product features awaiting implementation; operational mechanism: A detailed scope statement makes proposed work sufficiently clear to control additions; specific limitation: It supports decomposition and acceptance criteria.

B:

Transition and release plan is intended to prepare deployment, business handoff, training, cutover, and stabilization activities; that is different from the overlooked customer-support application release obligation to maintain an ordered inventory of agile product features awaiting implementation; operational mechanism: A transition plan describes how delivered capabilities will become supported operations; specific limitation: A technically complete product still needs readiness for real use.

D:

Work breakdown structure (WBS) is already serving decompose a fixed delivery scope into manageable work packages for estimating in the customer-support application release; the corrected plan must also address the unmet obligation to maintain an ordered inventory of agile product features awaiting implementation; functional evidence: A WBS organizes the complete project work into smaller deliverable-oriented components; qualification to consider: It is not the same as a chronological milestone calendar.