CompTIA PK0-005 (CompTIA Project+) Practice Test 35

Question 340

In the regional call-center cutover, the team proposes the practice Task board to visualize current work moving through columns such as queued, in progress, and done. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. Version control maintains a history of changes to files and code.
  2. Traceability makes it possible to verify that defined requirements were addressed.
  3. A dashboard consolidates metrics for quick monitoring.
  4. This approach displays workflow state and ownership of current tasks.

Explanation

Correct Answer

D:

This is observable evidence of Task board for the regional call-center cutover purpose to visualize current work moving through columns such as queued, in progress, and done; operational mechanism: A task board displays workflow state and ownership of current tasks; specific limitation: It usually gives less dependency detail than a project network diagram.

Incorrect Answers

A:

This behavior would demonstrate Version control system for track who changed source artifacts and allow review or restoration of earlier revisions, rather than Task board for visualize current work moving through columns such as queued, in progress, and done in the regional call-center cutover; the practical reason is: Version control maintains a history of changes to files and code; important boundary: It does not itself prioritize project risk or resource allocations.

B:

This behavior would demonstrate Requirements traceability matrix for connect each requirement to design elements, test cases, and acceptance evidence, rather than Task board for visualize current work moving through columns such as queued, in progress, and done in the regional call-center cutover; operational mechanism: Traceability makes it possible to verify that defined requirements were addressed; specific limitation: A task board alone does not show end-to-end requirement evidence.

C:

This behavior would demonstrate Project dashboard for present a compact set of current indicators and exceptions across project workstreams, rather than Task board for visualize current work moving through columns such as queued, in progress, and done in the regional call-center cutover; functional evidence: A dashboard consolidates metrics for quick monitoring; qualification to consider: A narrative status report can supply more context behind the numbers.

Question 341

The school district device refresh team has a specific outstanding requirement: name the one person answerable for the completion and approval of a deliverable. At the planning review, which action or practice is the most appropriate response?

  1. Confirm high-level solution design
  2. Consulted (C)
  3. Accountable (A)
  4. Stakeholder power-interest analysis

Explanation

Correct Answer

C:

Accountable (A) fits the school district device refresh requirement to name the one person answerable for the completion and approval of a deliverable; the practical reason is: Accountable ownership establishes final answerability for an outcome; important boundary: A well-designed RACI normally assigns one accountable owner per activity.

Incorrect Answers

A:

Confirm high-level solution design is intended to select a feasible architecture direction that meets the charter's major constraints, not to meet the school district device refresh requirement to name the one person answerable for the completion and approval of a deliverable; operational mechanism: Early solution design resolves critical technical assumptions for planning; specific limitation: Detailed build specifications may still be refined later.

B:

Consulted (C) is intended to seek subject matter input before deciding on a design that affects another team, not to meet the school district device refresh requirement to name the one person answerable for the completion and approval of a deliverable; the practical reason is: Consulted roles provide two-way advice that can influence a decision; important boundary: They are not simply passive recipients of a finished announcement.

D:

Stakeholder power-interest analysis is intended to decide which affected parties need close management versus routine communication, not to meet the school district device refresh requirement to name the one person answerable for the completion and approval of a deliverable; operational mechanism: Power-interest analysis evaluates influence and degree of concern for an initiative; specific limitation: It supports engagement strategy rather than assigning developer work packages.

Question 342

The log monitoring deployment earned value is $120,000. To produce an SPI of 0.80, what planned value PV would correspond to this EV?

  1. $1
  2. $96,000
  3. $150,000
  4. $120,000

Explanation

Correct Answer

C:

SPI = EV/PV, so PV = EV/0.80 = $150,000. These stated figures yield $150,000 for the requested planned value at target SPI in the log monitoring deployment case.

Incorrect Answers

A:

This is a unitless cost ratio, not planned value. The resulting $1 does not match the requested planned value at target SPI for the log monitoring deployment: the governing arithmetic is SPI = EV/PV, so PV = EV/0.80 = $150,000, yielding $150,000.

B:

This multiplies rather than divides by SPI. The resulting $96,000 does not match the requested planned value at target SPI for the log monitoring deployment: the governing arithmetic is SPI = EV/PV, so PV = EV/0.80 = $150,000, yielding $150,000.

D:

This yields SPI 1 rather than 0.8. The resulting $120,000 does not match the requested planned value at target SPI for the log monitoring deployment: the governing arithmetic is SPI = EV/PV, so PV = EV/0.80 = $150,000, yielding $150,000.

Question 343

In the regional help-desk rollout, the team proposes the practice Privacy impact assessment to evaluate how a new application collects, uses, shares, and retains personal information. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. Retention controls tie storage duration and disposal to policy and law.
  2. Privacy assessment identifies risk to individuals and needed safeguards before launch.
  3. Jurisdictional review connects processing location and affected people to legal requirements.
  4. Compliance evidence supports audits and demonstrations of conformity.

Explanation

Correct Answer

B:

This is observable evidence of Privacy impact assessment for the regional help-desk rollout purpose to evaluate how a new application collects, uses, shares, and retains personal information; functional evidence: Privacy assessment identifies risk to individuals and needed safeguards before launch; qualification to consider: A generic hardware inventory does not reveal data-processing exposure.

Incorrect Answers

A:

This behavior would demonstrate Retention and secure disposal schedule for specify how long sensitive project data is kept and how it is safely removed, rather than Privacy impact assessment for evaluate how a new application collects, uses, shares, and retains personal information in the regional help-desk rollout; functional evidence: Retention controls tie storage duration and disposal to policy and law; qualification to consider: Indefinite retention can conflict with privacy and storage duties.

C:

This behavior would demonstrate Regional privacy-law review for check which jurisdiction's privacy rules apply to cross-border customer processing, rather than Privacy impact assessment for evaluate how a new application collects, uses, shares, and retains personal information in the regional help-desk rollout; functional evidence: Jurisdictional review connects processing location and affected people to legal requirements; qualification to consider: A vendor's headquarters alone may not determine every applicable law.

D:

This behavior would demonstrate Compliance evidence collection for retain proof that required controls and approvals were applied during delivery, rather than Privacy impact assessment for evaluate how a new application collects, uses, shares, and retains personal information in the regional help-desk rollout; functional evidence: Compliance evidence supports audits and demonstrations of conformity; qualification to consider: A verbal assertion that a control exists may not satisfy an auditor.

Question 344

In the endpoint protection rollout, the team proposes the practice Detailed scope statement to specify boundaries, major deliverables, assumptions, and exclusions for project execution. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. A transition plan describes how delivered capabilities will become supported operations.
  2. This approach shows when planned work should happen and in what order.
  3. This approach makes proposed work sufficiently clear to control additions.
  4. A communication plan maps stakeholders to information needs and timing.
  5. The budget provides a cost reference for authorizing and tracking expenditure.
  6. The backlog captures work candidates and their relative product priority.

Explanation

Correct Answer

C:

This is observable evidence of Detailed scope statement for the endpoint protection rollout purpose to specify boundaries, major deliverables, assumptions, and exclusions for project execution; functional evidence: A detailed scope statement makes proposed work sufficiently clear to control additions; qualification to consider: It supports decomposition and acceptance criteria.

Incorrect Answers

A:

This behavior would demonstrate Transition and release plan for prepare deployment, business handoff, training, cutover, and stabilization activities, rather than Detailed scope statement for specify boundaries, major deliverables, assumptions, and exclusions for project execution in the endpoint protection rollout; functional evidence: A transition plan describes how delivered capabilities will become supported operations; qualification to consider: A technically complete product still needs readiness for real use.

B:

This behavior would demonstrate Project schedule for map activity dependencies, expected durations, resources, and milestones, rather than Detailed scope statement for specify boundaries, major deliverables, assumptions, and exclusions for project execution in the endpoint protection rollout; the practical reason is: A project schedule shows when planned work should happen and in what order; important boundary: Budget alone cannot reveal logical task constraints.

D:

This behavior would demonstrate Communications management plan for specify which audiences get which messages through what channel and frequency, rather than Detailed scope statement for specify boundaries, major deliverables, assumptions, and exclusions for project execution in the endpoint protection rollout; operational mechanism: A communication plan maps stakeholders to information needs and timing; specific limitation: It should include escalation and confidentiality where relevant.

E:

This behavior would demonstrate Project budget for estimate and baseline expected costs by activity, resource, or period, rather than Detailed scope statement for specify boundaries, major deliverables, assumptions, and exclusions for project execution in the endpoint protection rollout; the practical reason is: The budget provides a cost reference for authorizing and tracking expenditure; important boundary: It must reflect procurement and contingency assumptions where appropriate.

F:

This behavior would demonstrate Prioritized product backlog for maintain an ordered inventory of agile product features awaiting implementation, rather than Detailed scope statement for specify boundaries, major deliverables, assumptions, and exclusions for project execution in the endpoint protection rollout; the practical reason is: The backlog captures work candidates and their relative product priority; important boundary: Not every item is a committed sprint deliverable.

Question 345

The school district device refresh team has a specific outstanding requirement: avoid repeated handoffs by assigning design, build, and test capabilities within one stable team. At the planning review, which action or practice is the most appropriate response?

  1. Dedicated cross-functional team
  2. Adaptive delivery
  3. Timeboxed work
  4. Rolling-wave planning
  5. Predictive planning

Explanation

Correct Answer

A:

Dedicated cross-functional team fits the school district device refresh requirement to avoid repeated handoffs by assigning design, build, and test capabilities within one stable team; the practical reason is: Cross-functional team composition supports end-to-end delivery and rapid feedback; important boundary: Shared specialists can become bottlenecks if their allocation is not planned.

Incorrect Answers

B:

Adaptive delivery is intended to adjust a product backlog as customer feedback changes desired features, not to meet the school district device refresh requirement to avoid repeated handoffs by assigning design, build, and test capabilities within one stable team; functional evidence: Adaptive approaches embrace reprioritization and incremental feedback loops; qualification to consider: They still require scope and budget governance rather than unlimited untracked change.

C:

Timeboxed work is intended to protect a fixed short delivery interval while adjusting the amount of feasible work, not to meet the school district device refresh requirement to avoid repeated handoffs by assigning design, build, and test capabilities within one stable team; operational mechanism: Timeboxing constrains an iteration's duration and forces priority decisions; specific limitation: It does not guarantee that every initially proposed story will fit.

D:

Rolling-wave planning is intended to plan near-term work in detail while leaving distant uncertain work at higher level, not to meet the school district device refresh requirement to avoid repeated handoffs by assigning design, build, and test capabilities within one stable team; the practical reason is: Rolling-wave planning elaborates activities as reliable information becomes available; important boundary: It is progressive refinement, not a decision to abandon baselines altogether.

E:

Predictive planning is intended to keep scope and specifications stable before detailed design and implementation, not to meet the school district device refresh requirement to avoid repeated handoffs by assigning design, build, and test capabilities within one stable team; the practical reason is: Predictive delivery establishes substantial requirements and plans before execution; important boundary: Uncontrolled changes later normally require formal impact review.

Question 346

The branch-network refresh team has a specific outstanding requirement: carry out an approved solution adjustment using the agreed implementation plan. At the planning review, which action or practice is the most appropriate response?

  1. Maintain change-log status
  2. Update the approved project plan
  3. Perform change impact analysis
  4. Implement the authorized change

Explanation

Correct Answer

D:

Implement the authorized change fits the branch-network refresh requirement to carry out an approved solution adjustment using the agreed implementation plan; functional evidence: Implementation puts the approved change into the actual product or project workflow; qualification to consider: It follows assessment and authorization rather than replacing those controls.

Incorrect Answers

A:

Maintain change-log status is intended to record the decision, owner, implementation status, and closure evidence of every request, not to meet the branch-network refresh requirement to carry out an approved solution adjustment using the agreed implementation plan; functional evidence: Current change records support traceability and prevent requests from being lost; qualification to consider: They are broader than a list containing only the newly proposed features.

B:

Update the approved project plan is intended to reflect an authorized change in schedules, budget, and scope baselines as required, not to meet the branch-network refresh requirement to carry out an approved solution adjustment using the agreed implementation plan; functional evidence: Plan updates make an approved decision operational for subsequent tracking; qualification to consider: They should follow authorization rather than silently legitimize unauthorized work.

C:

Perform change impact analysis is intended to quantify effects on delivery date, cost, scope, quality, and risk before approval, not to meet the branch-network refresh requirement to carry out an approved solution adjustment using the agreed implementation plan; operational mechanism: Impact analysis gives authorized reviewers evidence about trade-offs of a proposed change; specific limitation: Implementing first would bypass the information needed for a sound decision.

Question 347

In the fraud analytics implementation, the team proposes the practice Quantitative risk assessment to estimate potential cost or completion-time effects using numeric probability models. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. This approach remains accountable for its triggers, status, and agreed treatment.
  2. This approach defines pre-agreed actions triggered by the named risk event.
  3. Quantitative analysis evaluates numerical exposure or distributions of possible outcomes.
  4. This approach provides another route when the first risk response is insufficient.

Explanation

Correct Answer

C:

This is observable evidence of Quantitative risk assessment for the fraud analytics implementation purpose to estimate potential cost or completion-time effects using numeric probability models; operational mechanism: Quantitative analysis evaluates numerical exposure or distributions of possible outcomes; specific limitation: It needs defensible assumptions and is not merely a high-medium-low label.

Incorrect Answers

A:

This behavior would demonstrate Risk owner for assign one individual to monitor a specific uncertainty and coordinate response, rather than Quantitative risk assessment for estimate potential cost or completion-time effects using numeric probability models in the fraud analytics implementation; functional evidence: A risk owner remains accountable for its triggers, status, and agreed treatment; qualification to consider: Ownership cannot be replaced by an unassigned item in a register.

B:

This behavior would demonstrate Contingency plan for specify what to do if a known anticipated risk actually materializes, rather than Quantitative risk assessment for estimate potential cost or completion-time effects using numeric probability models in the fraud analytics implementation; operational mechanism: A contingency plan defines pre-agreed actions triggered by the named risk event; specific limitation: It is activated by risk conditions rather than serving as the original delivery plan.

D:

This behavior would demonstrate Fallback plan for define a secondary response if the initial contingency action does not work, rather than Quantitative risk assessment for estimate potential cost or completion-time effects using numeric probability models in the fraud analytics implementation; operational mechanism: A fallback plan provides another route when the first risk response is insufficient; specific limitation: It should have activation criteria and available resources of its own.

Question 348

The warehouse scanning upgrade team has a specific outstanding requirement: display how much time or capacity is allocated to each activity over the schedule. At the planning review, which action or practice is the most appropriate response?

  1. Resource loading
  2. Sprint planning
  3. Schedule forecasting
  4. Schedule rebaselining

Explanation

Correct Answer

A:

Resource loading fits the warehouse scanning upgrade requirement to display how much time or capacity is allocated to each activity over the schedule; the practical reason is: Resource loading shows assignment demands across periods and people; important boundary: It exposes overload but does not by itself decide how to resolve it.

Incorrect Answers

B:

Sprint planning is intended to select a feasible set of prioritized backlog work against an iteration goal, not to meet the warehouse scanning upgrade requirement to display how much time or capacity is allocated to each activity over the schedule; operational mechanism: Sprint planning connects team capacity, product priority, and a usable near-term goal; specific limitation: It is not a formal long-term fixed-scope sign-off.

C:

Schedule forecasting is intended to predict likely finish dates using actual progress and remaining work, not to meet the warehouse scanning upgrade requirement to display how much time or capacity is allocated to each activity over the schedule; functional evidence: Forecasting projects a probable outcome without automatically changing the approved baseline; qualification to consider: The distinction preserves visibility into original commitments.

D:

Schedule rebaselining is intended to adopt a formally approved replacement schedule baseline following authorized major change, not to meet the warehouse scanning upgrade requirement to display how much time or capacity is allocated to each activity over the schedule; operational mechanism: Rebaselining changes the reference against which future variance is measured; specific limitation: Routine forecast updates should not erase the original approved baseline.

Question 349

The multisite wireless upgrade team has a specific outstanding requirement: resolve a time-sensitive ambiguity through immediate two-way exchange. At the planning review, which action or practice is the most appropriate response?

  1. Formal written notice
  2. Controlled confidential channel
  3. Archived project correspondence
  4. Synchronous conversation

Explanation

Correct Answer

D:

Synchronous conversation fits the multisite wireless upgrade requirement to resolve a time-sensitive ambiguity through immediate two-way exchange; operational mechanism: Synchronous communication enables live questioning and rapid clarification; specific limitation: It requires participants to overlap in time.

Incorrect Answers

A:

Formal written notice is intended to document a contractual decision for an external supplier with a durable record, not to meet the multisite wireless upgrade requirement to resolve a time-sensitive ambiguity through immediate two-way exchange; operational mechanism: Formal written communication provides an attributable and retrievable decision trail; specific limitation: A casual chat may not satisfy prescribed contract notice terms.

B:

Controlled confidential channel is intended to send sensitive delivery data only to authorized recipients using approved protection, not to meet the multisite wireless upgrade requirement to resolve a time-sensitive ambiguity through immediate two-way exchange; functional evidence: Confidential communication restricts disclosure through access and secure channels; qualification to consider: Convenience alone cannot override data-handling requirements.

C:

Archived project correspondence is intended to preserve decision and approval history for later handoff or audit, not to meet the multisite wireless upgrade requirement to resolve a time-sensitive ambiguity through immediate two-way exchange; functional evidence: Communication archiving retains retrievable evidence of what was agreed and when; qualification to consider: It is separate from merely notifying a person in real time.

Question 350

The identity-access migration team already uses Communicate adoption benefits to explain why new procedures matter and how stakeholders will be affected. A new workstream must also prepare users whose daily processes will change after a new IT rollout. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Train impacted employees
  2. Monitor vendor performance
  3. Communicate adoption benefits
  4. Hold project status updates

Explanation

Correct Answer

A:

Adding Train impacted employees addresses the new identity-access migration need to prepare users whose daily processes will change after a new IT rollout; Communicate adoption benefits already serves the separate need to explain why new procedures matter and how stakeholders will be affected; the practical reason is: Organizational change training enables staff to perform future workflows; important boundary: Technical deployment alone does not guarantee adoption.

Incorrect Answers

B:

Monitor vendor performance would instead address check a contractor's milestones and quality against the agreed SOW; the identity-access migration still needs to prepare users whose daily processes will change after a new IT rollout, in addition to its existing Communicate adoption benefits; the practical reason is: Vendor monitoring uses contractual deliverables and measures to detect slippage; important boundary: Paying an invoice without validation does not establish performance.

C:

Communicate adoption benefits is already present in the identity-access migration to explain why new procedures matter and how stakeholders will be affected; repeating it does not fulfill the distinct requirement to prepare users whose daily processes will change after a new IT rollout; functional evidence: Change communication builds understanding and reduces uncertainty about adoption; qualification to consider: Announcing a launch date without context can increase resistance.

D:

Hold project status updates would instead address share agreed progress and blockers with stakeholders at the scheduled cadence; the identity-access migration still needs to prepare users whose daily processes will change after a new IT rollout, in addition to its existing Communicate adoption benefits; the practical reason is: Regular status meetings expose current delivery health and near-term decisions; important boundary: They should be supported by traceable actions rather than vague optimism.