CompTIA PK0-005 (CompTIA Project+) Practice Test 118

Question 1170

For the claims-processing modernization, a draft plan relies only on Define a minimum viable product because the team wants to select the smallest usable feature set needed to test value and gain learning. A reviewer identifies a separate unmet obligation: sequence the switch from an old system to the new production environment. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Define a minimum viable product
  2. Plan go-live cutover
  3. Train the project team
  4. Plan operational training

Explanation

Correct Answer

B:

The claims-processing modernization plan must add Plan go-live cutover to sequence the switch from an old system to the new production environment; its current Define a minimum viable product is already intended to select the smallest usable feature set needed to test value and gain learning; functional evidence: Cutover planning coordinates timing, dependencies, verification, and recovery; qualification to consider: The team needs a rollback criterion for unacceptable release results.

Incorrect Answers

A:

Define a minimum viable product is already serving select the smallest usable feature set needed to test value and gain learning in the claims-processing modernization; the corrected plan must also address the unmet obligation to sequence the switch from an old system to the new production environment; the practical reason is: An MVP supports early real-world feedback with limited scope; important boundary: It is not permission to omit necessary security or acceptance conditions.

C:

Train the project team is intended to close tool or workflow knowledge gaps before work depends on new skills; that is different from the overlooked claims-processing modernization obligation to sequence the switch from an old system to the new production environment; functional evidence: Training improves team readiness to use unfamiliar methods and platforms; qualification to consider: An untrained assignment creates quality and schedule risk.

D:

Plan operational training is intended to prepare support staff and users to operate the delivered system after release; that is different from the overlooked claims-processing modernization obligation to sequence the switch from an old system to the new production environment; the practical reason is: Operational training closes adoption and support skill gaps before handoff; important boundary: Deployment without trained owners can leave an unusable service.

Question 1171

Before using Burndown chart on the customer-support application release, the steering group asks about its limitations. Which qualification specifically prevents an overbroad interpretation of this practice for the goal to show estimated work remaining across a sprint or release?

  1. They show possible mechanisms rather than measured causal proof.
  2. A visible correlation does not prove one variable causes the other.
  3. They can conceal added scope unless the backlog changes are also reviewed.
  4. Without control limits they do not establish formal statistical control.

Explanation

Correct Answer

C:

This is the actual limitation of Burndown chart when the customer-support application release uses it to show estimated work remaining across a sprint or release; operational mechanism: Burndown charts trend remaining work against time and a target trajectory; specific limitation: They can conceal added scope unless the backlog changes are also reviewed.

Incorrect Answers

A:

This warning concerns Fishbone diagram used to organize hypotheses about underlying causes of recurrent service defects, not the specified Burndown chart used to show estimated work remaining across a sprint or release in the customer-support application release; operational mechanism: Fishbone diagrams group possible causes into categories for investigation; specific limitation: They show possible mechanisms rather than measured causal proof.

B:

This warning concerns Scatter diagram used to test whether two numeric variables appear associated across observations, not the specified Burndown chart used to show estimated work remaining across a sprint or release in the customer-support application release; functional evidence: A scatterplot reveals direction and strength of a possible relationship; qualification to consider: A visible correlation does not prove one variable causes the other.

D:

This warning concerns Run chart used to plot an operational metric over time to spot patterns or trends, not the specified Burndown chart used to show estimated work remaining across a sprint or release in the customer-support application release; functional evidence: Run charts display observations in chronological order; qualification to consider: Without control limits they do not establish formal statistical control.

Question 1172

Before using Responsibility assignment matrix on the backup retention migration, the steering group asks about its limitations. Which qualification specifically prevents an overbroad interpretation of this practice for the goal to make ownership and consultation relationships explicit for important deliverables?

  1. It supports engagement strategy rather than assigning developer work packages.
  2. It avoids gaps and overlapping claims of authority.
  3. Detailed work packages and full schedules are developed subsequently.
  4. The communication plan can then tailor updates to their needs.

Explanation

Correct Answer

B:

This is the actual limitation of Responsibility assignment matrix when the backup retention migration uses it to make ownership and consultation relationships explicit for important deliverables; functional evidence: A RAM maps activities to roles and their responsibilities; qualification to consider: It avoids gaps and overlapping claims of authority.

Incorrect Answers

A:

This warning concerns Stakeholder power-interest analysis used to decide which affected parties need close management versus routine communication, not the specified Responsibility assignment matrix used to make ownership and consultation relationships explicit for important deliverables in the backup retention migration; operational mechanism: Power-interest analysis evaluates influence and degree of concern for an initiative; specific limitation: It supports engagement strategy rather than assigning developer work packages.

C:

This warning concerns Project charter used to formally authorize a project with objectives, high-level scope, and a named leader, not the specified Responsibility assignment matrix used to make ownership and consultation relationships explicit for important deliverables in the backup retention migration; functional evidence: The charter establishes project legitimacy and overarching direction; qualification to consider: Detailed work packages and full schedules are developed subsequently.

D:

This warning concerns Stakeholder register used to identify interested parties and their influence before engagement begins, not the specified Responsibility assignment matrix used to make ownership and consultation relationships explicit for important deliverables in the backup retention migration; the practical reason is: A stakeholder register records people and groups affected by the project; important boundary: The communication plan can then tailor updates to their needs.

Question 1173

The multisite wireless upgrade team already uses Real-time coauthoring to allow multiple analysts to edit the same requirements document simultaneously. A new workstream must also host distributed participants with audio, screen sharing, and meeting controls. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Calendar scheduler
  2. Real-time coauthoring
  3. Face-to-face workshop
  4. Video conference
  5. Conferencing platform

Explanation

Correct Answer

E:

Adding Conferencing platform addresses the new multisite wireless upgrade need to host distributed participants with audio, screen sharing, and meeting controls; Real-time coauthoring already serves the separate need to allow multiple analysts to edit the same requirements document simultaneously; operational mechanism: Conferencing tools enable remote synchronous sessions; specific limitation: They need accessibility and connectivity planning for attendees.

Incorrect Answers

A:

Calendar scheduler would instead address find common available times and distribute meeting invitations; the multisite wireless upgrade still needs to host distributed participants with audio, screen sharing, and meeting controls, in addition to its existing Real-time coauthoring; functional evidence: Calendaring tools coordinate schedules, reminders, and invitees; qualification to consider: They do not by themselves run a meeting or capture decisions.

B:

Real-time coauthoring is already present in the multisite wireless upgrade to allow multiple analysts to edit the same requirements document simultaneously; repeating it does not fulfill the distinct requirement to host distributed participants with audio, screen sharing, and meeting controls; operational mechanism: Coauthoring platforms synchronize edits and often expose change history; specific limitation: Uncoordinated local copies make version reconciliation harder.

C:

Face-to-face workshop would instead address resolve a complex sensitive disagreement where direct collaboration is valuable; the multisite wireless upgrade still needs to host distributed participants with audio, screen sharing, and meeting controls, in addition to its existing Real-time coauthoring; operational mechanism: In-person workshops support rich live engagement and physical collaboration; specific limitation: Travel and availability cost more than asynchronous channels.

D:

Video conference would instead address discuss a design visually with dispersed staff who need live interaction; the multisite wireless upgrade still needs to host distributed participants with audio, screen sharing, and meeting controls, in addition to its existing Real-time coauthoring; the practical reason is: Video meetings provide real-time conversation and shared visual context; important boundary: Time zones and connectivity can limit attendance.

Question 1174

Before using Defect log on the multisite wireless upgrade, the steering group asks about its limitations. Which qualification specifically prevents an overbroad interpretation of this practice for the goal to manage observed product faults with reproduction steps, severity, and correction status?

  1. Actual current problems belong in issue tracking.
  2. It is more product-error-specific than a broad project issue register.
  3. The underlying risk register holds event-level detail.
  4. They do not automatically guarantee task quality or completion.

Explanation

Correct Answer

B:

This is the actual limitation of Defect log when the multisite wireless upgrade uses it to manage observed product faults with reproduction steps, severity, and correction status; the practical reason is: A defect log tracks flaws found in a deliverable under test; important boundary: It is more product-error-specific than a broad project issue register.

Incorrect Answers

A:

This warning concerns Risk register used to record future uncertainties with probability, impact, owner, and planned response, not the specified Defect log used to manage observed product faults with reproduction steps, severity, and correction status in the multisite wireless upgrade; the practical reason is: The risk register tracks exposure before a potential event occurs; important boundary: Actual current problems belong in issue tracking.

C:

This warning concerns Risk report used to summarize significant current exposures, trends, and response effectiveness for decision makers, not the specified Defect log used to manage observed product faults with reproduction steps, severity, and correction status in the multisite wireless upgrade; the practical reason is: A risk report aggregates risk information for oversight; important boundary: The underlying risk register holds event-level detail.

D:

This warning concerns Time-tracking tool used to capture hours worked against tasks so effort and costs can be measured, not the specified Defect log used to manage observed product faults with reproduction steps, severity, and correction status in the multisite wireless upgrade; functional evidence: Time-tracking tools record labor consumption for billing and capacity analysis; qualification to consider: They do not automatically guarantee task quality or completion.

Question 1175

Before using Execute gap analysis on the regional help-desk rollout, the steering group asks about its limitations. Which qualification specifically prevents an overbroad interpretation of this practice for the goal to compare current performance with an agreed target and quantify the remaining difference?

  1. A capable supplier still must comply with contract and site controls.
  2. Sensitive internal details need not be shared indiscriminately.
  3. One kickoff workshop does not prove lasting uptake.
  4. A routine status note may describe progress without measuring that difference.

Explanation

Correct Answer

D:

This is the actual limitation of Execute gap analysis when the regional help-desk rollout uses it to compare current performance with an agreed target and quantify the remaining difference; the practical reason is: Gap analysis identifies missing capabilities or performance against a defined target state; important boundary: A routine status note may describe progress without measuring that difference.

Incorrect Answers

A:

This warning concerns Enforce vendor engagement rules used to ensure subcontractors follow agreed access, communication, and work protocols, not the specified Execute gap analysis used to compare current performance with an agreed target and quantify the remaining difference in the regional help-desk rollout; the practical reason is: Rules of engagement clarify permissible vendor behavior and escalation; important boundary: A capable supplier still must comply with contract and site controls.

B:

This warning concerns Issue external status reporting used to send a sponsor-approved project summary to an outside customer or partner, not the specified Execute gap analysis used to compare current performance with an agreed target and quantify the remaining difference in the regional help-desk rollout; the practical reason is: External status reports communicate relevant commitments beyond the internal team; important boundary: Sensitive internal details need not be shared indiscriminately.

C:

This warning concerns Reinforce the new behavior used to measure use of a new process and coach teams after initial rollout, not the specified Execute gap analysis used to compare current performance with an agreed target and quantify the remaining difference in the regional help-desk rollout; functional evidence: Adoption reinforcement sustains behavioral change after first training; qualification to consider: One kickoff workshop does not prove lasting uptake.

Question 1176

The delivery resource plan begins with a 520-hour backlog. Four engineers each deliver 30 work hours in each of two weeks. With no new work, how much backlog remains after that period?

  1. 240 hours
  2. 760 hours
  3. 520 hours
  4. 280 hours

Explanation

Correct Answer

D:

Remaining effort=520−2×4×30=280 hours. These stated figures yield 280 hours for the requested remaining effort in the delivery resource plan case.

Incorrect Answers

A:

This is completed effort, not the remainder. The resulting 240 hours does not match the requested remaining effort for the delivery resource plan: the governing arithmetic is Remaining effort=520−2×4×30=280 hours, yielding 280 hours.

B:

Adding completed work inflates remaining work. The resulting 760 hours does not match the requested remaining effort for the delivery resource plan: the governing arithmetic is Remaining effort=520−2×4×30=280 hours, yielding 280 hours.

C:

This is the original backlog. The resulting 520 hours does not match the requested remaining effort for the delivery resource plan: the governing arithmetic is Remaining effort=520−2×4×30=280 hours, yielding 280 hours.

Question 1177

The customer loyalty application team already uses Software development life cycle (SDLC) to describe the stages a software solution traverses from requirements to maintenance. A new workstream must also govern an initiative through defined management stages and business-case justification. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Waterfall
  2. PRINCE2
  3. Software development life cycle (SDLC)
  4. Kanban
  5. Extreme programming (XP)

Explanation

Correct Answer

B:

Adding PRINCE2 addresses the new customer loyalty application need to govern an initiative through defined management stages and business-case justification; Software development life cycle (SDLC) already serves the separate need to describe the stages a software solution traverses from requirements to maintenance; operational mechanism: PRINCE2 emphasizes continued business justification, roles, stage controls, and exceptions; specific limitation: It is a governance-oriented project method rather than a source-code branching practice.

Incorrect Answers

A:

Waterfall would instead address deliver a tightly specified integration using planned sequential phase approvals; the customer loyalty application still needs to govern an initiative through defined management stages and business-case justification, in addition to its existing Software development life cycle (SDLC); functional evidence: Waterfall commonly completes planned stages in sequence with formal stage outputs; qualification to consider: It is less accommodating of major late requirement changes than iterative approaches.

C:

Software development life cycle (SDLC) is already present in the customer loyalty application to describe the stages a software solution traverses from requirements to maintenance; repeating it does not fulfill the distinct requirement to govern an initiative through defined management stages and business-case justification; functional evidence: An SDLC model organizes software work through analysis, design, build, test, deployment, and support; qualification to consider: It is a life-cycle description rather than one specific project-governance method.

D:

Kanban would instead address visualize incoming tickets and limit work in progress to improve continuous flow; the customer loyalty application still needs to govern an initiative through defined management stages and business-case justification, in addition to its existing Software development life cycle (SDLC); the practical reason is: Kanban uses a visible workflow and work-in-progress limits to expose queues and bottlenecks; important boundary: It does not require fixed-length iterations or a prescribed sprint role set.

E:

Extreme programming (XP) would instead address improve code quality with pair programming, continuous integration, and test-first engineering; the customer loyalty application still needs to govern an initiative through defined management stages and business-case justification, in addition to its existing Software development life cycle (SDLC); operational mechanism: Extreme programming applies disciplined engineering practices and rapid developer feedback; specific limitation: It is a software development practice set, not an enterprise portfolio framework.

Question 1178

For the supplier onboarding portal, a draft plan relies only on Incremental delivery because the team wants to release usable functions in slices rather than waiting for the entire feature set. A reviewer identifies a separate unmet obligation: combine stage-gated infrastructure procurement with iterative application development. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Incremental delivery
  2. Dedicated cross-functional team
  3. Iterative prototyping
  4. Predictive planning
  5. Hybrid delivery

Explanation

Correct Answer

E:

The supplier onboarding portal plan must add Hybrid delivery to combine stage-gated infrastructure procurement with iterative application development; its current Incremental delivery is already intended to release usable functions in slices rather than waiting for the entire feature set; operational mechanism: Hybrid delivery intentionally applies different delivery methods to different workstreams; specific limitation: Its coordination plan must reconcile milestone dependencies and cadences.

Incorrect Answers

A:

Incremental delivery is already serving release usable functions in slices rather than waiting for the entire feature set in the supplier onboarding portal; the corrected plan must also address the unmet obligation to combine stage-gated infrastructure procurement with iterative application development; operational mechanism: Incremental work adds deployable capability in successive deliveries; specific limitation: Each increment increases usable scope even when underlying features are not redesigned.

B:

Dedicated cross-functional team is intended to avoid repeated handoffs by assigning design, build, and test capabilities within one stable team; that is different from the overlooked supplier onboarding portal obligation to combine stage-gated infrastructure procurement with iterative application development; functional evidence: Cross-functional team composition supports end-to-end delivery and rapid feedback; qualification to consider: Shared specialists can become bottlenecks if their allocation is not planned.

C:

Iterative prototyping is intended to show users successive mockups to discover usability requirements before final design; that is different from the overlooked supplier onboarding portal obligation to combine stage-gated infrastructure procurement with iterative application development; the practical reason is: Iterations test assumptions through repeated evaluation of a working model; important boundary: The purpose is learning and revision rather than declaring the first draft final.

D:

Predictive planning is intended to keep scope and specifications stable before detailed design and implementation; that is different from the overlooked supplier onboarding portal obligation to combine stage-gated infrastructure procurement with iterative application development; functional evidence: Predictive delivery establishes substantial requirements and plans before execution; qualification to consider: Uncontrolled changes later normally require formal impact review.

Question 1179

The hybrid meeting room expansion team already uses Control scope creep to stop informal feature additions from bypassing approved scope and change procedures. A new workstream must also recognize extra work that has been started without approved impact assessment. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Conduct a preliminary change review
  2. Control scope creep
  3. Uncontrolled change
  4. Update the approved project plan
  5. Refer the change to the change control board

Explanation

Correct Answer

C:

Adding Uncontrolled change addresses the new hybrid meeting room expansion need to recognize extra work that has been started without approved impact assessment; Control scope creep already serves the separate need to stop informal feature additions from bypassing approved scope and change procedures; functional evidence: An uncontrolled change bypasses the agreed decision workflow and threatens baselines; qualification to consider: A change can be useful and still require approval before inclusion.

Incorrect Answers

A:

Conduct a preliminary change review would instead address screen a request for completeness, duplication, and obvious policy conflicts before detailed analysis; the hybrid meeting room expansion still needs to recognize extra work that has been started without approved impact assessment, in addition to its existing Control scope creep; functional evidence: Preliminary review identifies invalid or incomplete requests early in the workflow; qualification to consider: It does not itself grant final approval for a material baseline change.

B:

Control scope creep is already present in the hybrid meeting room expansion to stop informal feature additions from bypassing approved scope and change procedures; repeating it does not fulfill the distinct requirement to recognize extra work that has been started without approved impact assessment; operational mechanism: Scope control compares requested work with the approved baseline and routes deviations through change control; specific limitation: Well-intentioned extras still consume time and resources unless authorized.

D:

Update the approved project plan would instead address reflect an authorized change in schedules, budget, and scope baselines as required; the hybrid meeting room expansion still needs to recognize extra work that has been started without approved impact assessment, in addition to its existing Control scope creep; operational mechanism: Plan updates make an approved decision operational for subsequent tracking; specific limitation: They should follow authorization rather than silently legitimize unauthorized work.

E:

Refer the change to the change control board would instead address obtain a decision from the designated cross-functional approval authority; the hybrid meeting room expansion still needs to recognize extra work that has been started without approved impact assessment, in addition to its existing Control scope creep; operational mechanism: The change control board approves or rejects requests within its defined authority; specific limitation: A project team cannot assume the sponsor delegated all approval power.

Question 1180

Two controls for a financial reporting migration risk have annual net benefits. Control A lowers probability from 60% to 50% at $3,000 cost; B lowers it to 40% at $8,500 cost. Impact is $130,000. What is the difference in their net benefits?

  1. −$13,000
  2. $10,000
  3. $7,500
  4. $17,500

Explanation

Correct Answer

C:

Net benefit A = $10,000 and B = $17,500 after fees; their absolute difference = $7,500. These stated figures yield $7,500 for the requested net-benefit difference in the financial reporting migration case.

Incorrect Answers

A:

Comparing gross reductions without accounting for different fees is incomplete. The resulting −$13,000 does not match the requested net-benefit difference for the financial reporting migration: the governing arithmetic is Net benefit A = $10,000 and B = $17,500 after fees; their absolute difference = $7,500, yielding $7,500.

B:

This is one response net benefit, not the gap between options. The resulting $10,000 does not match the requested net-benefit difference for the financial reporting migration: the governing arithmetic is Net benefit A = $10,000 and B = $17,500 after fees; their absolute difference = $7,500, yielding $7,500.

D:

This is the other response net benefit. The resulting $17,500 does not match the requested net-benefit difference for the financial reporting migration: the governing arithmetic is Net benefit A = $10,000 and B = $17,500 after fees; their absolute difference = $7,500, yielding $7,500.