CompTIA PK0-005 (CompTIA Project+) Practice Test 102

Question 1010

The service quality and software-release reporting quality team must bring the largest Pareto defect category from 48 incidents down to at most 35. What minimum number of incidents must it eliminate from that category?

  1. 48 incidents
  2. 83 incidents
  3. 35 incidents
  4. 13 incidents

Explanation

Correct Answer

D:

Largest category required reduction=48−35=13 incidents. These stated figures yield 13 incidents for the requested required reduction in the service quality and software-release reporting case.

Incorrect Answers

A:

This is original count. The resulting 48 incidents does not match the requested required reduction for the service quality and software-release reporting: the governing arithmetic is Largest category required reduction=48−35=13 incidents, yielding 13 incidents.

B:

Adding limit to count is not a required reduction. The resulting 83 incidents does not match the requested required reduction for the service quality and software-release reporting: the governing arithmetic is Largest category required reduction=48−35=13 incidents, yielding 13 incidents.

C:

This is the allowable remaining count, not reduction. The resulting 35 incidents does not match the requested required reduction for the service quality and software-release reporting: the governing arithmetic is Largest category required reduction=48−35=13 incidents, yielding 13 incidents.

Question 1011

In the engineering change-management system, the team proposes the practice Change risk assessment to evaluate potential outage, security, and customer effects before selecting deployment controls. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. Shared responsibility assigns control ownership according to the cloud service model.
  2. A maintenance window aligns expected service interruption with operations constraints.
  3. Risk assessment identifies what can fail and how to reduce exposure.
  4. Rollback planning sets recovery steps, checkpoints, and activation criteria.

Explanation

Correct Answer

C:

This is observable evidence of Change risk assessment for the engineering change-management system purpose to evaluate potential outage, security, and customer effects before selecting deployment controls; functional evidence: Risk assessment identifies what can fail and how to reduce exposure; qualification to consider: It should inform maintenance windows and rollback readiness.

Incorrect Answers

A:

This behavior would demonstrate Cloud shared-responsibility review for identify which change tasks belong to the hosted provider versus the customer, rather than Change risk assessment for evaluate potential outage, security, and customer effects before selecting deployment controls in the engineering change-management system; the practical reason is: Shared responsibility assigns control ownership according to the cloud service model; important boundary: Moving to hosted infrastructure does not erase customer access and configuration duties.

B:

This behavior would demonstrate Scheduled maintenance window for plan a disruptive infrastructure cutover during an approved low-impact period, rather than Change risk assessment for evaluate potential outage, security, and customer effects before selecting deployment controls in the engineering change-management system; functional evidence: A maintenance window aligns expected service interruption with operations constraints; qualification to consider: The window should be communicated and supported by recovery plans.

D:

This behavior would demonstrate Tested rollback plan for restore the prior known-good system state if release validation fails, rather than Change risk assessment for evaluate potential outage, security, and customer effects before selecting deployment controls in the engineering change-management system; functional evidence: Rollback planning sets recovery steps, checkpoints, and activation criteria; qualification to consider: A backup without a tested restoration procedure is insufficient assurance.

Question 1012

In the field technician scheduling rollout, the team proposes the practice Risk register to record future uncertainties with probability, impact, owner, and planned response. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. This approach tracks exposure before a potential event occurs.
  2. This approach tracks realized delivery problems through closure.
  3. This approach displays workflow state and ownership of current tasks.
  4. This approach aggregates risk information for oversight.

Explanation

Correct Answer

A:

This is observable evidence of Risk register for the field technician scheduling rollout purpose to record future uncertainties with probability, impact, owner, and planned response; operational mechanism: The risk register tracks exposure before a potential event occurs; specific limitation: Actual current problems belong in issue tracking.

Incorrect Answers

B:

This behavior would demonstrate Issue log for record active blockers with assignment, severity, progress, and resolution, rather than Risk register for record future uncertainties with probability, impact, owner, and planned response in the field technician scheduling rollout; operational mechanism: An issue log tracks realized delivery problems through closure; specific limitation: Forecast concerns alone belong in a risk register.

C:

This behavior would demonstrate Task board for visualize current work moving through columns such as queued, in progress, and done, rather than Risk register for record future uncertainties with probability, impact, owner, and planned response in the field technician scheduling rollout; functional evidence: A task board displays workflow state and ownership of current tasks; qualification to consider: It usually gives less dependency detail than a project network diagram.

D:

This behavior would demonstrate Risk report for summarize significant current exposures, trends, and response effectiveness for decision makers, rather than Risk register for record future uncertainties with probability, impact, owner, and planned response in the field technician scheduling rollout; operational mechanism: A risk report aggregates risk information for oversight; specific limitation: The underlying risk register holds event-level detail.

Question 1013

The procurement automation rollout team already uses Multifactor authentication to require a second independent factor for sensitive remote project access. A new workstream must also prevent a supplier from publishing unauthorized logos and claims in project materials. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Role-based permissions
  2. Multifactor authentication
  3. Company branding policy
  4. Restricted remote access

Explanation

Correct Answer

C:

Adding Company branding policy addresses the new procurement automation rollout need to prevent a supplier from publishing unauthorized logos and claims in project materials; Multifactor authentication already serves the separate need to require a second independent factor for sensitive remote project access; functional evidence: Branding controls govern approved use of company identity and public statements; qualification to consider: They address corporate policy rather than network packet encryption.

Incorrect Answers

A:

Role-based permissions would instead address assign system rights according to defined job responsibilities rather than shared accounts; the procurement automation rollout still needs to prevent a supplier from publishing unauthorized logos and claims in project materials, in addition to its existing Multifactor authentication; the practical reason is: Role-based access aligns permissions with job tasks and supports easier review; important boundary: It still requires least-privilege role design and timely removal.

B:

Multifactor authentication is already present in the procurement automation rollout to require a second independent factor for sensitive remote project access; repeating it does not fulfill the distinct requirement to prevent a supplier from publishing unauthorized logos and claims in project materials; functional evidence: MFA combines independent evidence of identity to reduce compromised-password risk; qualification to consider: It does not decide which files an authenticated user should see.

D:

Restricted remote access would instead address allow off-site administration only through approved secure access paths; the procurement automation rollout still needs to prevent a supplier from publishing unauthorized logos and claims in project materials, in addition to its existing Multifactor authentication; the practical reason is: Remote restrictions limit where and how privileged systems can be reached; important boundary: A valid password does not bypass network-access policy.

Question 1014

The asset-tracking solution team already uses Document and records management system to retain controlled versions of official records with retention and audit metadata. A new workstream must also centrally manage user identities and access relationships across applications. Which additional practice should be paired with the existing one to address the second, distinct need?

  1. Enterprise resource planning (ERP)
  2. Document and records management system
  3. Relational database
  4. Directory and identity service
  5. Financial accounting system

Explanation

Correct Answer

D:

Adding Directory and identity service addresses the new asset-tracking solution need to centrally manage user identities and access relationships across applications; Document and records management system already serves the separate need to retain controlled versions of official records with retention and audit metadata; operational mechanism: Identity services authenticate principals and support policy-driven access; specific limitation: They do not automatically specify a project's acceptance criteria.

Incorrect Answers

A:

Enterprise resource planning (ERP) would instead address integrate procurement, inventory, finance, and other core enterprise processes; the asset-tracking solution still needs to centrally manage user identities and access relationships across applications, in addition to its existing Document and records management system; operational mechanism: ERP unifies major back-office processes and shared business data; specific limitation: It is broader than a standalone customer sales pipeline.

B:

Document and records management system is already present in the asset-tracking solution to retain controlled versions of official records with retention and audit metadata; repeating it does not fulfill the distinct requirement to centrally manage user identities and access relationships across applications; operational mechanism: Electronic document and records management controls records lifecycles; specific limitation: It does more than publishing web page content.

C:

Relational database would instead address store transactional entities with structured queries and defined relationships; the asset-tracking solution still needs to centrally manage user identities and access relationships across applications, in addition to its existing Document and records management system; the practical reason is: Databases support consistent storage, retrieval, and updates of operational records; important boundary: An analytical warehouse has a different workload emphasis.

E:

Financial accounting system would instead address record financial transactions, accounts, and approved reporting data; the asset-tracking solution still needs to centrally manage user identities and access relationships across applications, in addition to its existing Document and records management system; operational mechanism: Financial systems support budgeting, accounting, reconciliation, and reporting; specific limitation: They are not the primary tool for user-story sequencing.

Question 1015

A five-week delivery resource plan capacity window offers 600 team-hours, and the work packages require 520. How many capacity hours remain unallocated before adding contingency?

  1. 80 hours
  2. 520 hours
  3. 600 hours
  4. 1120 hours

Explanation

Correct Answer

A:

Unused capacity=600−520=80 hours. These stated figures yield 80 hours for the requested unallocated capacity in the delivery resource plan case.

Incorrect Answers

B:

This is effort demand. The resulting 520 hours does not match the requested unallocated capacity for the delivery resource plan: the governing arithmetic is Unused capacity=600−520=80 hours, yielding 80 hours.

C:

This is total capacity, not what remains. The resulting 600 hours does not match the requested unallocated capacity for the delivery resource plan: the governing arithmetic is Unused capacity=600−520=80 hours, yielding 80 hours.

D:

Adding demand to capacity is not a remainder. The resulting 1120 hours does not match the requested unallocated capacity for the delivery resource plan: the governing arithmetic is Unused capacity=600−520=80 hours, yielding 80 hours.

Question 1016

For the mobile enrollment service, a draft plan relies only on Responsibility assignment matrix because the team wants to make ownership and consultation relationships explicit for important deliverables. A reviewer identifies a separate unmet obligation: identify interested parties and their influence before engagement begins. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Responsibility assignment matrix
  2. Responsible (R)
  3. Stakeholder register
  4. Project charter

Explanation

Correct Answer

C:

The mobile enrollment service plan must add Stakeholder register to identify interested parties and their influence before engagement begins; its current Responsibility assignment matrix is already intended to make ownership and consultation relationships explicit for important deliverables; functional evidence: A stakeholder register records people and groups affected by the project; qualification to consider: The communication plan can then tailor updates to their needs.

Incorrect Answers

A:

Responsibility assignment matrix is already serving make ownership and consultation relationships explicit for important deliverables in the mobile enrollment service; the corrected plan must also address the unmet obligation to identify interested parties and their influence before engagement begins; operational mechanism: A RAM maps activities to roles and their responsibilities; specific limitation: It avoids gaps and overlapping claims of authority.

B:

Responsible (R) is intended to identify the people who actually perform work on an assigned deliverable; that is different from the overlooked mobile enrollment service obligation to identify interested parties and their influence before engagement begins; functional evidence: Responsible roles execute the task needed to produce an output; qualification to consider: They are not necessarily the single final owner of its accountability.

D:

Project charter is intended to formally authorize a project with objectives, high-level scope, and a named leader; that is different from the overlooked mobile enrollment service obligation to identify interested parties and their influence before engagement begins; operational mechanism: The charter establishes project legitimacy and overarching direction; specific limitation: Detailed work packages and full schedules are developed subsequently.

Question 1017

In the digital-signature rollout, the team proposes the practice Share an opportunity to partner with another organization to capture a beneficial market opportunity. An independent reviewer wants observable evidence that the proposed mechanism is being used. Which behavior should the reviewer expect?

  1. Opportunity sharing allocates ownership or benefits to a partner better positioned to realize them.
  2. A realized risk becomes an issue requiring action, tracking, and escalation.
  3. Quantitative analysis evaluates numerical exposure or distributions of possible outcomes.
  4. Opportunity exploitation deliberately changes work to secure the positive outcome.
  5. Risk transfer uses contracts or insurance to allocate certain consequences to another party.

Explanation

Correct Answer

A:

This is observable evidence of Share an opportunity for the digital-signature rollout purpose to partner with another organization to capture a beneficial market opportunity; functional evidence: Opportunity sharing allocates ownership or benefits to a partner better positioned to realize them; qualification to consider: It differs from transferring an adverse loss to an insurer.

Incorrect Answers

B:

This behavior would demonstrate Risk-to-issue transition for move a forecast risk into active issue management after the event occurs, rather than Share an opportunity for partner with another organization to capture a beneficial market opportunity in the digital-signature rollout; the practical reason is: A realized risk becomes an issue requiring action, tracking, and escalation; important boundary: Keeping it only as a future possibility would hide a present delivery obstacle.

C:

This behavior would demonstrate Quantitative risk assessment for estimate potential cost or completion-time effects using numeric probability models, rather than Share an opportunity for partner with another organization to capture a beneficial market opportunity in the digital-signature rollout; the practical reason is: Quantitative analysis evaluates numerical exposure or distributions of possible outcomes; important boundary: It needs defensible assumptions and is not merely a high-medium-low label.

D:

This behavior would demonstrate Exploit an opportunity for take action that makes an identified beneficial event virtually certain, rather than Share an opportunity for partner with another organization to capture a beneficial market opportunity in the digital-signature rollout; the practical reason is: Opportunity exploitation deliberately changes work to secure the positive outcome; important boundary: It is stronger than enhancement, which merely raises the probability or value.

E:

This behavior would demonstrate Transfer a threat for shift specified financial consequences of loss to an insurer or supplier, rather than Share an opportunity for partner with another organization to capture a beneficial market opportunity in the digital-signature rollout; functional evidence: Risk transfer uses contracts or insurance to allocate certain consequences to another party; qualification to consider: It does not make the underlying event impossible or erase oversight duties.

Question 1018

The regulated-document archive team has a specific outstanding requirement: set aside schedule time to respond to identified uncertainty. At the planning review, which action or practice is the most appropriate response?

  1. Backlog refinement
  2. Resource leveling
  3. Schedule forecasting
  4. Contingency reserve

Explanation

Correct Answer

D:

Contingency reserve fits the regulated-document archive requirement to set aside schedule time to respond to identified uncertainty; functional evidence: Contingency reserves cover planned exposure to identified risks within the agreed management approach; qualification to consider: They should not conceal poor estimating or unauthorized scope increases.

Incorrect Answers

A:

Backlog refinement is intended to split and clarify upcoming user stories and reorder them for future development, not to meet the regulated-document archive requirement to set aside schedule time to respond to identified uncertainty; the practical reason is: Backlog refinement improves readiness and ordering before work is selected; important boundary: It does not itself constitute completion or acceptance of the stories.

B:

Resource leveling is intended to resolve a schedule where one specialist is assigned more simultaneous work than capacity allows, not to meet the regulated-document archive requirement to set aside schedule time to respond to identified uncertainty; the practical reason is: Resource leveling adjusts activity timing to account for availability constraints; important boundary: It can lengthen the critical path instead of preserving an impossible allocation.

C:

Schedule forecasting is intended to predict likely finish dates using actual progress and remaining work, not to meet the regulated-document archive requirement to set aside schedule time to respond to identified uncertainty; functional evidence: Forecasting projects a probable outcome without automatically changing the approved baseline; qualification to consider: The distinction preserves visibility into original commitments.

Question 1019

For the cloud workload relocation, a draft plan relies only on Smoothing because the team wants to reduce immediate tension by emphasizing areas of agreement. A reviewer identifies a separate unmet obligation: settle a dispute quickly through concessions from both sides. Which choice corrects the gap instead of mistaking the first activity for the second?

  1. Issue external status reporting
  2. Smoothing
  3. Compromise
  4. Record meeting action owners

Explanation

Correct Answer

C:

The cloud workload relocation plan must add Compromise to settle a dispute quickly through concessions from both sides; its current Smoothing is already intended to reduce immediate tension by emphasizing areas of agreement; functional evidence: Compromise achieves an acceptable midpoint with each party giving something up; qualification to consider: It may not fully satisfy either underlying need.

Incorrect Answers

A:

Issue external status reporting is intended to send a sponsor-approved project summary to an outside customer or partner; that is different from the overlooked cloud workload relocation obligation to settle a dispute quickly through concessions from both sides; operational mechanism: External status reports communicate relevant commitments beyond the internal team; specific limitation: Sensitive internal details need not be shared indiscriminately.

B:

Smoothing is already serving reduce immediate tension by emphasizing areas of agreement in the cloud workload relocation; the corrected plan must also address the unmet obligation to settle a dispute quickly through concessions from both sides; functional evidence: Smoothing foregrounds shared goals to maintain relationships temporarily; qualification to consider: It can leave the underlying substantive dispute unresolved.

D:

Record meeting action owners is intended to assign named participants and deadlines to decisions from a delivery coordination meeting; that is different from the overlooked cloud workload relocation obligation to settle a dispute quickly through concessions from both sides; operational mechanism: Action ownership makes execution follow-up possible after the conversation ends; specific limitation: Meeting attendance by itself does not ensure actions are completed.

Question 1020

The service-ticketing replacement team has a specific outstanding requirement: estimate the time needed for cumulative benefits to recover initial investment. At the delivery review, which action or practice is the most appropriate response?

  1. Existing client statement of work
  2. Predetermined client constraints
  3. Capital expenditure (CapEx)
  4. Current-state assessment
  5. Payback period

Explanation

Correct Answer

E:

Payback period fits the service-ticketing replacement requirement to estimate the time needed for cumulative benefits to recover initial investment; functional evidence: Payback period identifies how long it takes to recoup outlay; qualification to consider: It is not a comprehensive measure of risk or the time value of money.

Incorrect Answers

A:

Existing client statement of work is intended to identify binding delivery scope already promised in a client agreement, not to meet the service-ticketing replacement requirement to estimate the time needed for cumulative benefits to recover initial investment; functional evidence: An existing SOW establishes contractual work commitments and acceptance boundaries; qualification to consider: Discovery must honor those constraints rather than casually redefining them.

B:

Predetermined client constraints is intended to identify nonnegotiable customer requirements already agreed before project discovery, not to meet the service-ticketing replacement requirement to estimate the time needed for cumulative benefits to recover initial investment; the practical reason is: A predetermined client can impose existing acceptance, environment, and contracting constraints; important boundary: The delivery team should verify these commitments before proposing alternatives.

C:

Capital expenditure (CapEx) is intended to classify a purchased server that will provide benefits over multiple accounting periods, not to meet the service-ticketing replacement requirement to estimate the time needed for cumulative benefits to recover initial investment; operational mechanism: Capital expenditure generally funds long-lived assets and is treated under applicable capitalization rules; specific limitation: Classification depends on the organization's accounting policy and standards.

D:

Current-state assessment is intended to document present operational bottlenecks before designing a future workflow, not to meet the service-ticketing replacement requirement to estimate the time needed for cumulative benefits to recover initial investment; operational mechanism: A current-state assessment establishes how processes and systems work today; specific limitation: It provides the baseline against which change value is judged.

CompTIA Project+ (PK0-005) Practice Tests